Ivanhoe College

A four badminton court, single storey, multi-use sports hall with specialist timber sprung flooring, classrooms, and ancillary areas including changing facilities and a new reception.

Cost: £2.3 Million exc VAT Location: Ashby De La Zouche, Leicestershire Opened: Sept 2023
Read Full Case Study

Project Challenges

We have faced a variety of challenges throughout our time developing sports halls. Each project generally presents its own set of complications, sometimes relating to existing structures, surrounding areas or site conditions and in other cases, it’s purely about budget, keeping numerous funding partners happy, or meeting a deadline.

Close

Project Challenges

The site was on the playground of the existing school with a single access. The project was constructed in the aftermath of COVID, when the supply chain for construction materials was still broken. As a result, there was a risk of non-availability or long lead-ins on key products.

The site ownership was complicated and the school was in the centre of the town. This meant there were particular challenges bringing in mains services, with various parties involved including the Trust themselves, the town council and the county council. Records from the transfer of the school from the local authority to the Trust were not clear, which would eventually lead to solicitors needing to resolve complicated conveyancing matters in order to facilitate easements for the mains services.

Project Solution

Each unique set of circumstances, is thought about and considered, in depth, by Ball Hall at the outset of the project. We bring all of our previous experience and expertise to the fore and try where possible, to apply a combination of creative and pragmatic thinking to problem solve in each case.

Close

Project Solutions

We worked closely with the contractor to ensure key products arrived on time. This included providing them with a long lead-in before the works started so we could be sure the contractor wouldn’t start and be forced to stop through lack of materials. We also found some additional space on the school site to allow the contractor to purchase materials early and stock them on site so last minute delays and unknowns were avoided.

Bringing mains services from the road was challenging due to easement issues. Gas and water were installed, but it became clear electricity couldn’t be brought in by the completion date. We had anticipated this risk and agreed a plan with the contractor: the building was completed excluding M&E commissioning, sprung floor installation, and final snagging. The contractor then returned a few weeks later to finish. Thanks to early planning, this was done collaboratively and the client was delighted with the result.

Ball Hall Added Value

With all the difficulties of a project considered upfront and contingency built in for unforeseen events or conditions, Ball Hall deliver outstanding buildings for sport. A Ball Hall Sports Hall often exceeds expectation and consistently becomes a flag waving celebration for the organisation, with many further benefits that materialise over time.

Close

Ball Hall Added Value

One of the ways we added value on this project was by including a couple of our tried and tested contractors on the tender list. One of whom was successful.

This meant the client received a very competitive price (within the budget) and had the confidence of using someone who had built sports halls for us previously. It also meant that when there was a problem resolving the legals for the mains electric, the contractor was keen to work with us to arrive at a solution, as they were looking to impress not just on this project but also for future Ball Hall projects

Read Full Case Study
The sports hall is a great asset to the school. Ball Hall took us through the journey (including through the challenging covid times) and made the project a pleasure to be involved in.

BEN DUNCOMBE, HEAD OF ESTATES, IVANHOE COLLEGE

Read All Testimonials